Scope added after the freeze (S2)

An outage campaign has its scope frozen. A late order is then proposed for it, so it becomes a scope change that must be decided before the order is assigned.

Recorded simulation replay — generated from an actual DSLCore network run (CORR-S2-235519). Pacing is normalised for viewing; the Technical view shows the recorded timings. Nothing on this page is live.

OrchestratorMobile plant workFixed plant workHaul road workShutdownsStockPurchasingFinanceOrchestratorFixed plant workShutdowns

Step by step

Key moment The scope being frozen, the late order waiting as a change, and the manager deciding it. The other steps are the background every story shares.

    This step in detail

    Checked against the reference flow

    S2 — Scope added after the freeze is a change to be decided before the work order is assigned. The network's specification declares the messages this flow involves. Every one of them appears in this recording. It also contains messages outside the reference flow: work.assign_campaign, work.readiness_changed.

    1. ✓ campaign.scope_frozen
    2. ✓ campaign.scope_change_requested
    3. ✓ campaign.scope_change_decided