Commissioning & Hold Point Manager
Manages commissioning plans, test packages, prerequisites, test execution and evidence through controlled hold points, with release and closeout decisions.
- Commissioning
- Commissioning management
- Hold points
- Test packages
- Commissioning evidence
The operational need
Commissioning is the boundary between a generator being built and its handover to operations. Tests have to run in an agreed sequence, each with its prerequisites satisfied or formally waived, and moving from one stage to the next depends on evidence reaching the right authority. When a material test fails, the stage needs to stop until the problem is cleared, with the reasons on record.
How the work flows
Commissioning program → Stage → Test package → Prerequisite → Test execution → Hold point report → Release decision
Each stage is gated by hold points. Reaching one requires a hold point report carrying the evidence bundle and a count of open issues, followed by an explicit release decision from the configured authority: release, release with conditions, hold or rework. A failed test, missing evidence, a configuration change, an unavailable network or a safety concern is recorded as a commissioning exception, which must be cleared before the hold point it affects is released.
What it records
- Commissioning programs — the program agreed with the network, its connection type, planned window and status.
- Commissioning stages — ordered stages with entry and exit criteria and a maximum output.
- Test packages — planned tests such as protection, SCADA, reactive power and ride-through, with procedure, window and witness requirement.
- Prerequisites — conditions to be satisfied or waived before a test is authorised.
- Test executions — each run’s result, observations and configuration snapshot.
- Hold points and hold point reports — gates with their release criteria, and the evidence submitted against them.
- Release decisions — the authority’s decision and any conditions attached.
- Commissioning exceptions — issues blocking release, with category, severity and owner.
Who would use it
Commissioning managers and engineers, test witnesses, and the authorities who review hold point reports and decide releases.
Adapting it to your organisation
This is a working demonstration and a developed starting point, not a universal procedure. An implementation is tailored and validated against your organisation's terminology, roles and responsibilities, workflow states, approval rules, reporting, evidence requirements, integrations and existing data.
Where specialist systems already perform engineering, telemetry, financial or analytical functions, they stay in place. DSLCore holds the governed operational layer around them: workflow, decisions, approvals, actions, evidence and reporting.